Tin tức mã cổ phiếu

PAP: Correction of Report on changing the plan on using capital

08/05/2025
On May 07, 2025, Petro Vietnam Phuoc An Port Investment & Operation Joint Stock Company announced the correction of Report No. 1725/PAP-TCHC on changing the plan for using capital/proceeds from the offering/issuance as follows:
- Old information:
Bidding package name Value (VND)
1. Pay expenses related to bidding packages under the contractor selection plan Phase 1 of Phuoc An Port and Logistics Service Area Project were approved by the General Meeting of Shareholders and the Board of Directors approved the adjustment, specifically: 50,000,000
  • Consult on the appraisal of request documents and contractor selection results for the bidding package Construct, supervise, and consult on ports, embankments, land leveling and treatment, roads, internal bridges, water supply and drainage, electrical systems, and auxiliary works; provide insurance – Phuoc An Port (Phase 1)
273,135,706,901
  • XL01 package: Implement construction of ground leveling and treatment - Phuoc An Port (Phase 1)
108,061,604,676
  • XL02 package: Implement construction of wharves, embankments to protect the shore, roads, internal bridges, water supply and drainage, electrical systems, and auxiliary works - Phuoc An Port (Phase 1)
1,238,774,548
  • GS1 package: Consult supervision of construction implementation of ground leveling and treatment - Phuoc An Port (Divergence 1)
7,625,286,855
  • GS2 package: Consult and supervise the construction of port, embankment, road, internal bridge, water supply and drainage, electrical system, and auxiliary works - Phuoc An Port (Phase 1)
200,000,000
  • Consult on making requests, evaluating proposal documents for Procurement Package 1, Procurement Package 2, and the consulting and supervising package for the supply and installation of port equipment - Phuoc An Port (Phase 1)
50,000,000
  • Consult and evaluate request documents and contractor selection results for Procurement Package 1, Procurement Package 2, and the consulting and supervising package for the supply and installation of port equipment - Phuoc An Port (Phase 1)
1,072,097,556
  • Construction Insurance Package
160,928,845,175
  • Procurement Package 1 Supply and install specialized equipment (including financial costs such as opening L/C, guarantee)
2,793,444,289
  • Procurement Package 2 Supply and install Reach Stacker, empty container forklift, and tractor
1,419,200,000
  • Procurement package 6 Supply and install trailers.
425,040,000
  • Procurement package 7 Supply and installation of weighing stations
23,000,000,000
Total 580,000,000,000
- New information:
Bidding package name Value (VND)
1. Pay expenses related to bidding packages under the contractor selection plan Phase 1 of Phuoc An Port and Logistics Service Area Project were approved by the General Meeting of Shareholders and the Board of Directors approved the adjustment, specifically: 557,000,000,000
  • Consult on the appraisal of request documents and contractor selection results for the bidding package Construct, supervise, and consult on ports, embankments, land leveling and treatment, roads, internal bridges, water supply and drainage, electrical systems, and auxiliary works; provide insurance – Phuoc An Port (Phase 1)
50,000,000
  • Consult on the appraisal of request documents and contractor selection results for the bidding package Construct, supervise, and consult on ports, embankments, land leveling and treatment, roads, internal bridges, water supply and drainage, electrical systems, and auxiliary works; provide insurance – Phuoc An Port (Phase 1)
273,135,706,901
  • XL01 package: Implement construction of ground leveling and treatment - Phuoc An Port (Phase 1)
108,061,604,676
  • XL02 package: Implement construction of wharves, embankments to protect the shore, roads, internal bridges, water supply and drainage, electrical systems, and auxiliary works - Phuoc An Port (Phase 1)
1,238,774,548
  • GS1 package: Consult supervision of construction implementation of ground leveling and treatment - Phuoc An Port (Divergence 1)
7,625,286,855
  • GS2 package: Consult and supervise the construction of port, embankment, road, internal bridge, water supply and drainage, electrical system, and auxiliary works - Phuoc An Port (Phase 1)
200,000,000
  • Consult on making requests, evaluating proposal documents for Procurement Package 1, Procurement Package 2, and the consulting and supervising package for the supply and installation of port equipment - Phuoc An Port (Phase 1)
50,000,000
  • Consult and evaluate request documents and contractor selection results for Procurement Package 1, Procurement Package 2, and the consulting and supervising package for the supply and installation of port equipment - Phuoc An Port (Phase 1)
1,072,097,556
  • Construction Insurance Package
160,928,845,175
  • Procurement Package 1 Supply and install specialized equipment (including financial costs such as opening L/C, guarantee)
2,793,444,289
  • Procurement Package 2 Supply and install Reach Stacker, empty container forklift, and tractor
1,419,200,000
  • Procurement package 6 Supply and install trailers.
425,040,000
  • Procurement package 7 Supply and installation of weighing stations
23,000,000,000
Total 580,000,000,000